Day 6: Friday Nov 13 2009











It's been a week since work first started.I'm quite amazed at how fast progress is being made. The foreman indicated that things start slowing down when the dry wall is put into place. Day 7 is when they'll use a jackhammer and drill the concrete floor and install the plumbling lines. Promises to be a 'loud' day.
As well as this, I've completed purchasing the kitchen appliances and washer/dryer.
Of all the new changes in the basement, one that has to be corrected is the pool door. The wrong one was ordered but to stay on schedule they installed it!